Our Process
I’m interested in a Homeful building - where do I start?
The best place to start is booking a meeting with us, to discuss your needs, timeframe and budget. From there, we are able to launch into Stage One (see below), to assess the feasibility of your new home/studio/space.
Our Homeful process can be quicker + more streamlined than a custom design process as we have already done much of the design thinking for you! Our Homeful process takes approx 6 months. See below for a breakdown of our process.
Stage One: Your Feasibility Package
Site visit and analysis
Gather all property, site, regulatory and authority information
Define the approval process relevant to your project/ property and scope of work
Prepare full brief and initial estimate of probable costs
Prepare initial site plan and selected Homeful building arrangement
Discuss the customisations you need
Provide our list of Homeful preferred builders
Time estimation: 6-8 weeks
Stage Two: Design Development + Development Approval
Customise your Homeful template
Customised 3D model
Refine materials and prepare design moodboards
Design Development Drawings for DA submission
Approval of DA drawings by clients
Submit the project for Development/Planning approval or exemption
Address any requests for further information
Time estimation: 4-6 weeks
Approval time estimation: 2-7 weeks, depending on complexity of site (Councils have 42 days to make their assessment, if they ask for further information this will be longer)
We proceed with the following stage whilst your project is being assessed by council.
Stage Three: Documentation + Building Approval
Documentation drawings for building approval
Complete specification of works including client preferences and all regulatory items
Prepare internal elevations
Approval of documentation drawings by clients
Obtain consultant certificates and sign offs
Engage Building Surveyor and obtain Certificate of Likely Compliance
Submit and obtain plumbing approval from council if required (subject to Building Act)
Submit and obtain building approval from council if required (subject to Building Act)
Time estimation: 6-8 weeks
Approval time estimation: 4-6 weeks, depending on complexity of site
Stage Four: Detailed Design/Selections
Select interior and selection package
Prepare detailed specification, selections and colour schedules
Time estimation: 4 weeks
Stage Five: Construction Management
optional - incurs additional fees
Hand over to chosen builder
Site visits + assistance as required
Construction management timeframe: Dependent on site conditions + builder availability
We always aim to work in a time efficient and considered way.
We also manage all your consultants + approvals, and assist you in seeking cost estimates + pricing from builders.
Please keep in mind that these are nominal times and depending on the situation and the property, extra time may be required.
Contingencies should be put in place for extended time frames due to site, consultant and council time frames and extended decision making.
Total design + approval time estimation: 6-9 months, pending council time frames